K&Z Cabinet Co. · Manager Meeting · June 12, 2026
Pre-Manager
Meeting Notes
The full packet of reports handed out ahead of the June 12, 2026 manager meeting — sales booked, jobs bid, production status, listing backlog, and PM billing — reproduced page by page. Use the arrows below or your ← → keys to flip through.
$3.14M
New contracts booked · 2 jobs (Jun)
$9.62M
Bid in May · 9 jobs (Dennis + Joe)
380
Cabinets listed in 2 weeks
463 → 229
Listing backlog drawn down · June
200 / 500
Boxes turned to production vs. goal
$2.08M
PM billing submitted · May
01Monthly Sales Report — Jun 2026
02Jobs Bid — Dennis Chan (May)
03Jobs Bid — Joe Resurreccion (May)
04Production Notes — 5/19–6/8
05Listing & Backlog — June
06Production Turnover & PM Workload
07Project Manager May Billing
Report 01 · Sales
Monthly Sales Report · Jun 2026
New contracts written this month · printed Thursday, June 11, 2026
| Date | Job Name | Contract Amt | Complete Date |
|---|---|---|---|
| 6/4/2026 | Marshall Elementary School — WSM | $147,570.00 | 5/1/2028 |
| 6/11/2026 | Washington Middle School Transformation 2B | $2,993,840.00 | 10/24/2028 |
| Total · 2 Projects | $3,141,410.00 | ||
Average Job
$1,570,705.00
Jobs over $50,000
2
Jobs under $10,000
0
Report 02 · Estimating
Jobs Bid by Dennis Chan
May 2026 · Customer key — Direct = direct to owner · Neg = negotiated
| Bid Date | Project | Customer | Bid Value | Bid Result |
|---|---|---|---|---|
| 5/7/2026 | Ofelia Valdez Yeager Eastside E.S. (OVYEES) | Direct | $425,720.00 | Not Low |
| 5/14/2026 | Space Shuttle Exhibit & Education Building | Neg | $98,690.00 | |
| 5/15/2026 | Emerson Village | Neg | $5,801,160.00 | |
| 5/21/2026 | Albert Einstein Academy Charter High School | Neg | $978,200.00 | |
| 5/27/2026 | Corona High School — Classroom Buildings | Neg | $189,740.00 | |
| 5/29/2026 | SPED Admin. TK Bldgs. at Endeavour E.S. | Direct | $158,650.00 | Not Low |
| Total · 6 bids | $7,651,560.00 | |||
Report 03 · Estimating
Jobs Bid by Joe Resurreccion
May 2026 · Customer key — Direct = direct to owner · Neg = negotiated · Green Sheet
| Bid Date | Project | Customer | Bid Value | Bid Result |
|---|---|---|---|---|
| 5/13/2026 | Mission Bay High School — WSM | Green Sheet | $528,100.00 | |
| 5/19/2026 | FUSD New Elementary School #37 | Neg | $1,035,870.00 | |
| 5/28/2026 | City of Indio — Indio Police Headquarters | Direct | $407,150.00 | |
| Total · 3 bids | $1,971,120.00 | |||
Report 04 · Production
Production Notes
K&Z Cabinet Co. · 5/19/26 – 6/8/26
Focus on Jobs
- 6199 / 6198All Bldgs
- 6116Taft
- 6197Pedley
- 6210Carmel Del Mar · starting
Shop Notes
The shop is off and running with our hot summer jobs — we now have plenty of work to keep the shop very busy. The shop is back on full overtime in order to meet the current deadlines. The listing department listed 380 cabinets in the past 2 weeks & are doing a great job.
Problem Areas
— none noted —
Cabinet Count · daily average
5/19 – 5/25
32.8
5/26 – 6/1
32.4
6/2 – 6/8
31.2
Report 05 · Listing
Listing & Backlog
June 2026 · Opening balance 463 · Hand-off (out) vs. Listing (in), running balance
| Day | Hand-off | Listing | Balance | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Job # | Amt | Job # | Amt | Job # | Amt | Job # | Amt | Job # | Amt | Job # | Amt | ||
Report 06 · PM Report (Prepared by Troy A. Zerillo · 6/12/2026)
Turned Over to Production
June · cabinets released to the shop floor
| Date | Job | Boxes | Description |
|---|---|---|---|
| 6/3/2026 | GUSO | 130 | Only cabinets — whole job |
| 6/11/2026 | Beswick ES | 60 | Bldg C & E |
| 6/11/2026 | Malibu | 10 | Life Skill Class |
| Total turned over | 200 | Goal 500 | |
PM Workload · active projects & billable
| PM | Active Projects | Billable |
|---|---|---|
| Hugo | 22 | $6,591,025 |
| Sergio | 18 | $5,527,849 |
| Saul | 12 | $3,585,861 |
| Total | 52 | $15,704,735 |
Report 07 · Billing
Project Manager May Billing
By PM · Billed / Approved / Pending / Cut
PM · Hugo
| Job | Project | Billed | Approved |
|---|---|---|---|
| 6129 | Lincoln HS Pkg 7,8,9,10 & 14 | $82,825.59 | — |
| 6159 | FUSD New Secondary Academy | $717,468.25 | $545,176.82 |
| 6163 | Pacliffi HS | $18,925.43 | $13,252.02 |
| 6170 | Don Lugo HS | $15,391.65 | $15,391.65 |
| 6173 | Charles R Drew | $33,829.20 | $33,829.20 |
| 6175 | The Commons | $17,565.00 | $6,674.00 |
| 6177 | New Haven ES | $75,485.12 | $74,845.90 |
| 6178 | SBWD | $15,524.00 | — |
| 6183 | Ontario Ballpark | $115,222.31 | $115,222.31 |
| 6204 | Redlands City Hall | $18,920.20 | $18,920.20 |
| 6205 | Santee Community Center | $9,338.97 | $0.00 |
| 6210 | Carmel Del Mar School | $47,806.00 | $0.00 |
| Hugo Total · Cut $98,349.59 | $823,512.59 | — | |
PM · Saul
| Job | Project | Billed | Approved |
|---|---|---|---|
| 6121 | Kennedy ES | $159,767.30 | $68,990.00 |
| 6148 | Delevan ES | $18,450.41 | $18,450.41 |
| 6152 | ELAC Nursing | $17,933.00 | $0.00 |
| 6155 | LAPC Academic West Bldg | $36,103.32 | $36,103.32 |
| 6174 | Bobier ES | $77,186.93 | $77,186.93 |
| 6193 | Santa Ana Main Library | $14,409.50 | $13,689.02 |
| 6206 | Canoga Park HS | $16,552.00 | $16,552.00 |
| Saul Total · Cut $109,430.78 | $230,971.68 | — | |
PM · Sergio
| Job | Project | Billed | Approved |
|---|---|---|---|
| 6050 | San Pedro | $105,210.90 | — |
| 6138 | King Chavez | $13,010.25 | $2,427.25 |
| 6154 | Holmes ES | $10,905.00 | $10,905.00 |
| 6155 | Albert Einstein ES | $78,480.00 | $44,235.00 |
| 6185 | Palm MS | $4,750.00 | $4,750.00 |
| 6191 | RUHS Wellness | $100,772.00 | $79,894.00 |
| 6196 | Ontario Sports | $17,762.15 | $17,762.15 |
| 6198 | Hendrick, Hidden Springs & W | $55,866.65 | $55,866.65 |
| 6199 | Cloverdale, Honey Hollow & Sw | $183,901.00 | $183,901.00 |
| Sergio Total · Pending $105,210.90 · Cut $65,706.00 | $599,761.00 | — | |
Grand Total · Billed
$2,079,362.13
Approved
$1,454,026.53
Pending
$209,560.49
Cut
$421,776.41