Chris ran the production schedule job-by-job — July, then August, then a September look-ahead. ("Good day" against a line item means the ship date is confirmed.) The headline: July is under control — almost everything turned in, Carmel started shipping, Lincoln ships in a week or two, and several buildings got zeroed out.
August is where the gaps are. A lot is still not turned in, waiting on mockups, RFIs, and key schedules — the Delavan mockup approval (≈300 line items sit behind it), Canoga Park's PLAM-color RFI, and Navio Building E's lock key schedule. Most of August is fine once a few answers land.
September is about keeping slipping jobs honest. ELAC / South Gate is still framing; rather than rolling the date 8–9 weeks at a time, get a realistic date from the super or put it on hold — and don't buy material 3–4 months early. The meeting closed on the same discipline as the managers': once a job is in production, point of no return.
"If we just keep moving it 8, 9 weeks out, then we're just fooling ourselves." — on the slipping jobs.
Confirming a ship date per line item gives installers and GCs a straight answer and lets production plan around a real commitment — not a guess.
Production · PM — the whole walk
Don't roll a date 8–9 weeks at a time. Call the super for a realistic date, or put it on hold. "It's on the schedule" doesn't mean it'll be there — and don't buy material 3–4 months early.
PM — ELAC / South Gate
Order premium cherry and reject mineral-streak boards before accepting. Once it's milled it's ours, and a touch-up doubles the finishing cost on a 20–40-year city-hall job.
Dennis · Production — LATTC cherry
Where reveals align to a window or picture frame (Nob Hill), get the drywall up and measure with a laser before takeoff — otherwise the panel ends up short on one corner.
PM · Field — Nob Hill
Once a job's turned in, no changes. A late change is a change order, added cost, and an 8–10 week delay — and it stops Sammy's crew mid-job. Send the release letter.
Chris · Dennis — the close
When a job keeps sliding, don't sign a no-cost change order that gives away the escalation cost. Move it right, hold it, and keep the delay claim alive.
Dennis · PM — ELAC no-cost CO