K&Z Meetings · June 2026

Manager Meeting

Job-Cost Review 7 jobs walked Break-even line · 25%
01 Summary

Dennis walked the team job-by-job through actual vs. estimated cost on seven recently closed projects. The recurring story: jobs are won and lost in the field, not the shop. Material and production held up well across the board — but installation hours and engineering hours were where the money moved, for better and worse.

The honest scoreboard was mixed. Homes (48%) and Welcome Resource (32%) cleared the line comfortably; Trade-in College only reached 24% break-even after a hard-fought $52K change order, having bled $161K on installation alone. Kearney limped in at 2% — barely above water. The thread tying it together: catch problems early, watch the field, and fight for the change order.

"We win some and we lose some. If we take 25% — that's overhead." — the line every PM runs against.

02 Highlights job by job
03 Lessons for the whole company

Review the scope early

"Is this really ours?" The questions asked at takeoff save the job in production. Trade-in's metal work was never challenged — and it cost us.

Estimating · PM · Production — Trade-in College

Watch installation hours

The shop can do everything right and the job still bleeds in the field. Track install hours against estimate weekly — that's where the biggest swings live.

Field · PM — $161K lost on Trade-in install

Engineering hours add up fast

600 engineering/listing hours = $24K, three months of one person. A "simple" bookcase job isn't simple if nobody's tracking the hours going into it.

Engineering · Listing — Trade-in 254 → 600 hrs

Change orders are the saving grace

Document it, price it, send it. The gap between a loss and break-even is the change order you fought for. $52K on one job, $20K on another.

PM · Estimating — Trade-in · Pacific High

Be thorough — don't cut corners

"The cost of ignorance is tons of money settling." Most losses aren't one big mistake — they're a hundred details nobody questioned.

Everyone — the whole meeting, really

Stopping out still costs you

When drafting is stopped out, someone else does your shop drawings — and we pay for it. Factor that cost in; it quietly eats the margin.

Engineering · PM — Kearney

04 To Dos action items