Dennis walked the team job-by-job through actual vs. estimated cost on seven recently closed projects. The recurring story: jobs are won and lost in the field, not the shop. Material and production held up well across the board — but installation hours and engineering hours were where the money moved, for better and worse.
The honest scoreboard was mixed. Homes (48%) and Welcome Resource (32%) cleared the line comfortably; Trade-in College only reached 24% break-even after a hard-fought $52K change order, having bled $161K on installation alone. Kearney limped in at 2% — barely above water. The thread tying it together: catch problems early, watch the field, and fight for the change order.
"We win some and we lose some. If we take 25% — that's overhead." — the line every PM runs against.
"Is this really ours?" The questions asked at takeoff save the job in production. Trade-in's metal work was never challenged — and it cost us.
Estimating · PM · Production — Trade-in College
The shop can do everything right and the job still bleeds in the field. Track install hours against estimate weekly — that's where the biggest swings live.
Field · PM — $161K lost on Trade-in install
600 engineering/listing hours = $24K, three months of one person. A "simple" bookcase job isn't simple if nobody's tracking the hours going into it.
Engineering · Listing — Trade-in 254 → 600 hrs
Document it, price it, send it. The gap between a loss and break-even is the change order you fought for. $52K on one job, $20K on another.
PM · Estimating — Trade-in · Pacific High
"The cost of ignorance is tons of money settling." Most losses aren't one big mistake — they're a hundred details nobody questioned.
Everyone — the whole meeting, really
When drafting is stopped out, someone else does your shop drawings — and we pay for it. Factor that cost in; it quietly eats the margin.
Engineering · PM — Kearney