Scheduling Standards · Production Department
K&Z operates on an 8-week production window, which begins from the confirmed ship date. This period allows adequate time for material ordering and cabinet production. Two weeks before the scheduled shipping date, the Project Manager must confirm and finalize the shipping arrangements. In the final week before delivery, the Project Manager is responsible for verifying that the jobsite is fully prepared to receive the shipment, ensuring a smooth delivery process.
| Time from Ship Date | Action Required |
|---|---|
| 8 weeks before Production | Start production window — order materials and begin cabinet production |
| 2 weeks before PM | Project Manager confirms ship date and finalizes logistics |
| 1 week before PM | Project Manager verifies jobsite readiness and confirms delivery |
| Ship Date Delivery | Cabinets delivered to jobsite |