Cabinet Lock Guideline

How K&Z reads locks on a job — what lock, where it goes, and how it's keyed. Follow these five steps in order.

★
The one rule
If the spec and the drawing don't match — RFI it before production. Never assume.
1
What lock to use → the Spec tells you
The specs name the lock product: Olympus 500DR, Corbin 0737, or National. Use ANSI Grade 1 locks with metal strike plates.
2
Where locks go → the Drawings win
The architectural drawings and keynotes decide the lock locations — they beat the general spec wording.
Build it

Spec says "all doors & drawers locked" AND the drawing shows the lock symbol → build it locked. No question.

Ask first

Spec says it but there's no symbol on the drawing → stop and RFI it. The PM holds and verifies before turn-in.

3
How they're keyed → the District's Keying Schedule is final
The District's Keying Schedule says which rooms, what's keyed alike, and the master key — and it can even change where locks go (for example, "no locks on lower cabinets"). It beats everything, even a "lock all" keynote. Request it early — locks need 2–3 weeks lead time. Don't finalize locks until it's back.
4
"100% locks" from the estimator = money, not a build order
When the estimator marks 100% locks, it means the cost is covered — not that every cabinet ships locked. The PM still verifies before production.
5
Contradiction? RFI it — before production
Any conflict goes to an RFI before the job is turned in. Once it's in production, a change becomes a change order + 8–10 week delay.

Where this comes from