The purpose of the K&Z engineering department is to create shop drawings that function for shop production and fulfill the architect's intent per plans, specs, and details.
b.This purpose should always be the focus while processing shop drawings and submittals.
2Receive New Project
a.Receive project from engineering manager.
b.Review project based on scope of work and drawing requirements:
i.K&Z Job Summary
ii.Plans and Specs
iii.Schedule
iv.K&Z bid proposal
v.Subcontract scope of work
vi.Addendums
vii.RFIs
c.Find incorrect drawing details or discrepancies between architectural drawings and K&Z standards.
d.Identify potential problems for the project.
e.Break down drawings based on the project schedule, so that you can draw in sequential order.
3Attend Startup Meeting
a.Review drawings and specs with project manager and estimator.
b.Identify the project sequence to draw shop drawings accordingly.
c.The startup meeting will aid in understanding potential problem areas.
d.Collectively, the team will decide how to proceed with these problems—whether they should submit RFIs, not draw certain items, put drawings on hold, etc.
e.After the meeting, write out a summary of action items for the project.
4Process Shop Drawings & Submittals
a.Setup timelines for completing the drawings based on priorities and deadlines (talk with the engineering manager to discuss these timelines).
b.Work on submittals in conjunction with the shop drawings—hardware, etc.
c.Develop a list of RFI items, and review them with the project manager:
i.Focus on critical items needed for clarification.
ii.Leave in-house items to figure out with K&Z production team.
iii.Keep the RFI to one page if possible.
iv.Provide answers and alternate proposed items for the architect.
d.Work on CCP or MCP certifications; request these from Woodwork Institute standards.
e.Check any long lead items—plastic laminate, hardware—with purchasing.
f.Make more drawing changes according to any pre-production requests.
g.Go over complicated millwork details with production.
h.Review completed shop drawings with the engineering manager.
i.Review completed shop drawings with the PM prior to submitting to the architect.
j.If the architect returns shop drawings with "revise and resubmit," work with PMs to address redline issues.
k.Work on drawings for change order submittals, additions, and omissions.
l.Create hardware takeoff based on the latest approved drawings and change orders. Then send the list over to production and purchasing.
5Engineer Expectations
a.The project engineer should be thorough, detailed, and fully understand the following components of their projects: